Building a Free Standing
Town Home

Sydney

November 2017 - November 2018

Stage One

The Beginning

Land is getting levelled and prepared for footings, big and exciting project is starting.

November 2017

Stage Two

The Foundation Of The Building

Footings have been dug out and the steel is going in, very important part of the building.

November 2017

Stage Three

The Foundation Of The Building

The concrete is poured in footings. We make sure those yellow caps are on steel bars. Safety always comes first.

November 2017

Stage Four

The Basement

Block work in the basement is completed. Now we are perfectly levelling ground preparing it for the ground slab.

December 2017

Stage Five

The Construction Is In Progress

Ground steel mesh is ready and stormwater pits are in place, ready for the concrete.

Friday, November 18, 2017

Stage Six

The Look From A Distance

Ground steel mesh is ready and stormwater pits are in place, ready for the concrete.

December 2017

Stage Seven

The Construction Is In Progress

Pouring concrete on the ground slab.

December 2017

Stage Eight

The Construction Is In Progress

Pouring concrete on the ground slab.

December 2017

Stage Nine

The Look From Above

Birds view of the half done concrete slab. Tomorrow the second half will be completed.

December 2017

Stage Ten

Bricklayers are working very hard. The townhomes are shaping up.

April 2018

Stage Eleven

Steel

Steel, Steel, Steel! This is what a suspended slab preparation looks like.

May 2018

Stage Twelve

The Construction Is In Progress

2 town homes to go.

June 2018

Stage Thirteen

The Roof

We are nearly there! Roof and tiles to go.

July 2018

Stage Fourteen

The Finish

Plants and buffalo grass is placed, getting ready for SALE!

November 2018